Phase 0 Research: Infrastructure Operations & Deployment Automation

Date: 2026-04-20
Feature: Infrastructure Operations & Deployment Automation
Status: Complete

Research Findings

Blue-Green Deployment Strategy

Decision: Docker Compose with Nginx Proxy Manager for traffic switching
Rationale: Provides zero-downtime deployments by maintaining two identical production environments (blue/green) and switching traffic via reverse proxy configuration updates
Alternatives Considered: Kubernetes (too complex for current scale), Docker Swarm (limited networking features), Manual deployment scripts (prone to human error)

Backup & Recovery Solution

Decision: Restic for encrypted backups + MariaDB dump scripts + automated validation
Rationale: Restic provides deduplication, encryption, and cloud storage support. Combined with native database dumps ensures complete system state capture
Alternatives Considered: Borg Backup (steeper learning curve), rsync only (no encryption/deduplication), commercial solutions (cost constraints)

Monitoring Stack

Decision: Prometheus + Grafana + AlertManager + Node Exporter + cAdvisor
Rationale: Industry-standard monitoring stack with extensive community support, flexible alerting rules, and container-native metrics collection
Alternatives Considered: Zabbix (more complex setup), Nagios (older architecture), Datadog (commercial cost)

Container Security Hardening

Decision: Docker security hardening with non-root users, read-only filesystems, capability dropping, and Trivy scanning
Rationale: Provides defense-in-depth security while maintaining functionality. Trivy offers comprehensive vulnerability scanning
Alternatives Considered: Podman (better security but ecosystem compatibility issues), Kubernetes security policies (overkill for current scale)

Multi-NAS Architecture

Decision: QNAP for primary services, ASUSTOR for backup/monitoring registry
Rationale: Leverages existing hardware investment, provides geographic separation for critical services, and maintains established SSH key authentication
Alternatives Considered: Cloud hosting (recurring costs, data sovereignty concerns), Single NAS (single point of failure)

SSL Certificate Management

Decision: Certbot with Let's Encrypt + automated renewal via cron jobs
Rationale: Free, automated certificate management with established reliability. Integration with Nginx Proxy Manager simplifies deployment
Alternatives Considered: Commercial CAs (cost), Self-signed certificates (browser warnings), Cloudflare certificates (dependency on external service)

Secrets Management

Decision: Environment files with .gitignore + SSH key authentication
Rationale: Simple, secure approach that works across both NAS environments. No additional infrastructure required
Alternatives Considered: HashiCorp Vault (complex setup), Docker Swarm secrets (limited to single host), Infisical/SOPS (additional learning curve)

Technical Decisions Summary

  1. Docker Compose as primary orchestration tool
  2. Blue-Green deployment pattern for zero downtime
  3. Restic for backup encryption and deduplication
  4. Prometheus/Grafana stack for monitoring
  5. Nginx Proxy Manager for reverse proxy and SSL termination
  6. Trivy for container vulnerability scanning
  7. Environment files for secrets management
  8. SSH key authentication for cross-NAS communication

Implementation Constraints

  • Must maintain existing QNAP/ASUSTOR IP addresses (192.168.10.8/9)
  • Must preserve current data storage locations
  • Must integrate with existing Gitea Actions CI/CD pipeline
  • Must comply with ADR-016 security requirements
  • Must support Thai language documentation per project standards

Success Metrics Alignment

All technical decisions support the success criteria defined in the specification:

  • 99.9% uptime through redundant infrastructure
  • 30-second alert generation via Prometheus monitoring
  • 4-hour RTO through automated backup validation
  • Zero-downtime deployments via blue-green strategy
  • 100% security compliance via container hardening

Next Steps

Proceed to Phase 1: Design & Contracts with these technical foundations established.