251209:0000 Backend Test stagenot finish & Frontend add Task 013-015
This commit is contained in:
@@ -126,15 +126,15 @@ graph TB
|
||||
|
||||
### Phase 1: Foundation (2-3 weeks)
|
||||
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| ---------------------------------------------- | --------------------------- | -------- | -------- | -------------- | ------------ |
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| ---------------------------------------------- | --------------------------- | -------- | -------- | ------------- | ------------ |
|
||||
| [BE-001](./TASK-BE-001-database-migrations.md) | Database Setup & Migrations | P0 | 2-3 days | 🔴 Not Started | None |
|
||||
| [BE-002](./TASK-BE-002-auth-rbac.md) | Auth & RBAC Module | P0 | 5-7 days | 🔴 Not Started | BE-001 |
|
||||
|
||||
### Phase 2: Core Infrastructure (3-4 weeks)
|
||||
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| ------------------------------------------------- | -------------------------- | -------- | ---------- | -------------- | -------------- |
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| ------------------------------------------------- | -------------------------- | -------- | ---------- | ------------- | -------------- |
|
||||
| [BE-013](./TASK-BE-013-user-management.md) | User Management | P1 | 5-7 days | 🔴 Not Started | BE-001, BE-002 |
|
||||
| [BE-012](./TASK-BE-012-master-data-management.md) | Master Data Management | P1 | 6-8 days | 🔴 Not Started | BE-001, BE-002 |
|
||||
| [BE-003](./TASK-BE-003-file-storage.md) | File Storage (Two-Phase) | P1 | 4-5 days | 🔴 Not Started | BE-001, BE-002 |
|
||||
@@ -143,23 +143,23 @@ graph TB
|
||||
|
||||
### Phase 3: Business Modules (4-5 weeks)
|
||||
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| ------------------------------------------------ | --------------------- | -------- | --------- | -------------- | ---------------------------------- |
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| ------------------------------------------------ | --------------------- | -------- | --------- | ------------- | ---------------------------------- |
|
||||
| [BE-005](./TASK-BE-005-correspondence-module.md) | Correspondence Module | P1 | 7-10 days | 🔴 Not Started | BE-001~004, BE-006, BE-012, BE-013 |
|
||||
| [BE-007](./TASK-BE-007-rfa-module.md) | RFA Module | P1 | 8-12 days | 🔴 Not Started | BE-001~004, BE-006, BE-012, BE-013 |
|
||||
|
||||
### Phase 4: Supporting Modules (2-3 weeks)
|
||||
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| -------------------------------------------------- | ------------------------- | -------- | -------- | -------------- | -------------------------- |
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| -------------------------------------------------- | ------------------------- | -------- | -------- | ------------- | -------------------------- |
|
||||
| [BE-008](./TASK-BE-008-drawing-module.md) | Drawing Module | P2 | 6-8 days | 🔴 Not Started | BE-001~004, BE-012 |
|
||||
| [BE-009](./TASK-BE-009-circulation-transmittal.md) | Circulation & Transmittal | P2 | 5-7 days | 🔴 Not Started | BE-001~003, BE-006, BE-012 |
|
||||
| [BE-010](./TASK-BE-010-search-elasticsearch.md) | Search & Elasticsearch | P2 | 4-6 days | 🔴 Not Started | BE-001, BE-005, BE-007 |
|
||||
|
||||
### Phase 5: Supporting Services (1 week)
|
||||
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| --------------------------------------------- | ------------------------ | -------- | -------- | -------------- | -------------- |
|
||||
| ID | Task | Priority | Effort | Status | Dependencies |
|
||||
| --------------------------------------------- | ------------------------ | -------- | -------- | ------------- | -------------- |
|
||||
| [BE-011](./TASK-BE-011-notification-audit.md) | Notification & Audit Log | P3 | 3-5 days | 🔴 Not Started | BE-001, BE-002 |
|
||||
|
||||
---
|
||||
@@ -190,10 +190,11 @@ graph TB
|
||||
|
||||
### Phase 4: Supporting Features (Week 9)
|
||||
|
||||
| Task | Title | Priority | Effort | Dependencies |
|
||||
| ------------------------------------------------------- | ---------------------------- | -------- | -------- | -------------- |
|
||||
| [TASK-FE-008](./TASK-FE-008-search-ui.md) | Search & Global Filters | P2 | 3-4 days | FE-003, BE-010 |
|
||||
| [TASK-FE-009](./TASK-FE-009-dashboard-notifications.md) | Dashboard & Notifications UI | P3 | 3-4 days | FE-003, BE-011 |
|
||||
| Task | Title | Priority | Effort | Dependencies |
|
||||
| ---------------------------------------------------------- | ---------------------------- | -------- | -------- | -------------- |
|
||||
| [TASK-FE-008](./TASK-FE-008-search-ui.md) | Search & Global Filters | P2 | 3-4 days | FE-003, BE-010 |
|
||||
| [TASK-FE-009](./TASK-FE-009-dashboard-notifications.md) | Dashboard & Notifications UI | P3 | 3-4 days | FE-003, BE-011 |
|
||||
| [TASK-FE-013](./TASK-FE-013-circulation-transmittal-ui.md) | Circulation & Transmittal UI | P2 | 5-7 days | FE-005, BE-009 |
|
||||
|
||||
### Phase 5: Administration (Weeks 10-11)
|
||||
|
||||
@@ -202,6 +203,8 @@ graph TB
|
||||
| [TASK-FE-010](./TASK-FE-010-admin-panel.md) | Admin Panel & Settings UI | P2 | 5-7 days | FE-002, FE-005, BE-012, BE-013 |
|
||||
| [TASK-FE-011](./TASK-FE-011-workflow-config-ui.md) | Workflow Configuration UI | P2 | 5-7 days | FE-010, BE-006 |
|
||||
| [TASK-FE-012](./TASK-FE-012-numbering-config-ui.md) | Document Numbering Config UI | P2 | 3-4 days | FE-010, BE-004 |
|
||||
| [TASK-FE-014](./TASK-FE-014-reference-data-ui.md) | Reference Data & Lookups UI | P3 | 3-5 days | FE-010, BE-012 |
|
||||
| [TASK-FE-015](./TASK-FE-015-security-admin-ui.md) | Security & System Admin UI | P2 | 5-7 days | FE-010, BE-002, BE-011 |
|
||||
|
||||
---
|
||||
|
||||
@@ -231,7 +234,7 @@ graph TB
|
||||
#### Sprint 9-10: Supporting Modules (4 weeks)
|
||||
|
||||
- Week 18-19: Drawing Module (BE-008)
|
||||
- Week 20: Circulation & Transmittal (BE-009)
|
||||
- Week 20: Circulation & Transmittal (BE-009, FE-013)
|
||||
- Week 21: Search & Elasticsearch (BE-010)
|
||||
- _Milestone:_ Complete document ecosystem
|
||||
|
||||
@@ -313,16 +316,6 @@ graph TB
|
||||
- Search & filter
|
||||
- **Why Critical:** Core business document type
|
||||
|
||||
### TASK-BE-006: Workflow Engine
|
||||
|
||||
- **Type:** Core Infrastructure
|
||||
- **Key Deliverables:**
|
||||
- DSL parser and validator
|
||||
- State machine management
|
||||
- Guard and effect executors
|
||||
- History tracking
|
||||
- **Related ADR:** [ADR-001](../05-decisions/ADR-001-unified-workflow-engine.md)
|
||||
|
||||
### TASK-BE-007: RFA Module
|
||||
|
||||
- **Type:** Business Module
|
||||
@@ -377,7 +370,7 @@ graph TB
|
||||
|
||||
## 🔗 Dependencies Graph
|
||||
|
||||
```
|
||||
```mermaid
|
||||
BE-001 (Database)
|
||||
├── BE-002 (Auth)
|
||||
│ ├── BE-004 (Doc Numbering)
|
||||
|
||||